Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

All lines are relevant for on prem. For SaaS- only the lines that are marked for SaaS

Column week is the estimated number of weeks the project will take

Topic
SaaS
High availability
Webex
MS Teams
Time
Week
from start
Resources / Comments

Preparing system requirements

X

V

V

V

8 hours

1

Initial installation and requirements verification

X

V

V

V

4 hours

1

Configuration finalization and additional installation

V

V

V

V

4 hours

2

Proxy configuration

X

V

V

6 hours

For MS Teams proxy only

Webex Pre load data for cache

V

X

V

X

4 hours

2

loading existing rooms and users

For Ethical wall- run in learning mode

V

X

V

V

2 weeks

3-4

Build policy cache by running EW in learning mode
No customer resources for this stage

Test and verify policies. Modify as needed

V

X

V

V

4 hours

4

Handling existing content

V

X

V

NA

2 weeks

3-4

Optionally handling existing content that violates EW policies. No customer resources for this stage

Training and enrollment

V

X

V

V

4 hours

5

Further testing

V

X

V

V

4 hours

5

Go Live

V

X

V

V

8 hours

Monitor and tune system

Info

On a SaaS installation , it is will take AGAT 48 hours to set up the SaaS service