How much time does it take to install SphereShield for MS Teams / Webex on an environment for POC / Prod?
It depends on the complexity of the environment, but these are the expected time frame for a single deployment.
For lines marked for High availability add additional 30% for planning
All lines are relevant for on prem. For SaaS- only the lines that are marked for SaaS
Column week is the estimated number of weeks the project will take
Topic | SaaS | High availability | Webex | MS Teams | Time | Week | Resources / Comments |
---|---|---|---|---|---|---|---|
Preparing system requirements | X | V | V | V | 8 hours | 1 |
|
Initial installation and requirements verification | X | V | V | V | 4 hours | 1 |
|
Configuration finalization and additional installation | V | V | V | V | 4 hours | 2 |
|
Proxy configuration | X | V |
| V | 6 hours |
| For MS Teams proxy only |
Webex Pre load data for cache | V | X | V | X | 4 hours | 2 | loading existing rooms and users |
For Ethical wall- run in learning mode | V | X | V | V | 2 weeks | 3-4 | Build policy cache by running EW in learning mode |
Test and verify policies. Modify as needed | V | X | V | V | 4 hours | 4 |
|
Handling existing content | V | X | V | NA | 2 weeks | 3-4 | Optionally handling existing content that violates EW policies. No customer resources for this stage |
Training and enrollment | V | X | V | V | 4 hours | 5 |
|
Further testing | V | X | V | V | 4 hours | 5 |
|
Go Live | V | X | V | V | 8 hours |
| Monitor and tune system |
On a SaaS installation it will take AGAT 48 hours to set up the SaaS service